Hillsborough
roundabouts
one step closer
A plan to change several intersections on Hillsborough Street into
roundabouts moved one step closer to reality following a bond referendum
on Tuesday, Oct. 11.
Nearly 70 percent of Raleigh
voters who participated in the election approved a request by the city
to borrow $60 million
for a Street Improvement Bond. Some
of that money – $3 million – is earmarked for the roundabout project.
However,
don’t look for any construction crews just yet. The bond money
will not even be available until July 1, 2006, and then a lot of decisions
must be made before building begins.
“We will probably retain a design consultant, and then work with
the university and the Hillsborough Street Partnership (a citizen’s
group) in deciding on locations,” said Eric Lamb, transportation
services manager for the city’s Public Works Department. “The
process is going to be citizen-driven.”
When the project was initially
introduced, planners envisioned constructing 11 roundabouts – most
of them between Gorman Street and Oberlin Road – at
a price of about $15 million. Those plans fell through, and the city is approaching
the project on a much smaller scale, calling for two or three roundabouts.
However, the goals of the project have not changed.
“This project began with two tenets – one was to improve
pedestrian safety and the other was to boost economic development in
the area,” Lamb said. “The
question for us is, ‘Where can we do the best job of building the
roundabouts based on those two criteria?’”
Hillsborough Street
would be reduced to two lanes where the roundabouts are placed. The design
would likely also include medians and wider sidewalks.
It is expected
that traffic flow would lighten as drivers access faster routes to and
from
downtown.
Posted
Oct. 28, 2005
Return to the Bulletin homepage
|