Project Summary
-
Total Project Cost
$ 79,371,700
Total Phase I & II
$32,806,500
Phase I
$46,565,200
Phase II
-
Phase I
132,000 GSF
-
Scope:
Relocation of Chemical Engineering and Material Science and Engineering.
-
Phase II
141,00 GSF
-
Scope:
Relocation of Computer Science and Electrical Engineering departments.
|
|