Greek Village Development Project
Greek Village Site Plan
Participation
  1. Corporations interested in pursuing this project must commit between May 1, and August 1, 2007 in order to be included in Phase 1 which includes the first four building lots. Selection of lots will be first come first served (by date, not time), with consideration given to chapters who wish to build near their present house.
  2. Corporations must place a deposit of no less than $25,000 in earnest money for the right to participate in this project. Funds will be credited against future charges for infrastructure. Funds may be paid through the NC State Foundation and will be held in account by the University.
  3. Corporations must complete all items on the Greek Village Participation Checklist within 90 days of submitting a Letter of Commitment and earnest money.
  4. Corporations will share the cost of infrastructure (roads, sidewalks, utilities) with the University according to the following schedule:

    Option A
    100% Upfront

    Option B
    50% Upfront,
    50% over 10 Years

    Phase 1

    $315,000

    $360,000

    Phase 2

    $350,000

    $400,000

    Phase 3

    $385,000

    $440,000


  5. With either option, Corporations must pay the upfront portion of their infrastructure assessment prior to execution of their ground-lease document.
  6. Corporations will have 18 months from the time they commit to the project to commence construction on their chapter house. Once started, Corporations will have 18 months to complete construction and occupy their house.
  7. Corporations may establish accounts within the NC State Foundation to accept donations from alumni for the purpose of funding portions of their chapter house that are deemed for “educational use” by the IRS. Corporations may also fund their infrastructure assessments through the Foundation.
  8. University is committed to the next steps:

April 2007

Engineering/Design firm will be selected to begin design work for Phases 1 and 2 infrastructure

May 1 - August 1, 2007

Chapters may submit earnest money and letter of commitment to reserve one of four sites for Phase 1. Four commitments are needed to proceed with the project.

January 2008

Infrastructure work is slated to begin for Phase 1

August 2008

Construction of four houses to begin

August 2009

First new houses will be occupied

 